Business

A Diverse Energy Portfolio Is Essential for the City’s Power Reliability

Petr Fajmon, CEO of Teplárny Brno, portrait

Tags: , , , , , , , ,

Brno is preparing for a major overhaul of its heating systems in the coming years. The city’s utility provider, Teplárny Brno, plans to decrease its natural gas consumption by integrating a variety of energy sources, such as biomass, waste-to-energy, and nuclear power from Dukovany. CEO Petr Fajmon emphasises that this diversification is vital for maintaining a dependable energy supply.

Looking at the current state of the European energy sector, what trend do you consider most important?

No single, universal solution will work for all cities. I see the future in a combination of the sources available to a particular region. In some places, this is geothermal energy; in others, it is heat from industry, wastewater or data centres. Every city has different conditions and can utilise them to find its own solution. The common foundation is a high-quality network that allows sources to be combined and their mix gradually adjusted according to availability, economic factors, and consumer needs. This is where district heating’s real advantage lies. In Brno, we supply over 100,000 households and operate nearly 300 kilometres of steam and hot water pipelines. The decisions we make today will shape the city’s functioning for decades to come. With such responsibility, we must consider the entire system, from energy production right through to its efficient delivery to customers.

In which specific projects can this transformation already be seen?

It is already evident in several places. At the Brno-North plant, we built a new biomass plant that enables combined heat and power production. Moreover, we transport the biomass by rail, so we do not burden the local area with additional lorry traffic. However, the transformation is not just about building new power sources. We also need to modernise the network that distributes heat throughout the city. That is why we continue converting steam pipes to hot water pipes, which minimise heat loss and reduce operating costs. The third aspect involves greater integration between the heating and electricity sectors. At Červený mlýn, we use combined cycle technology and an electrode boiler, which provides ancillary services for the Czech transmission system. Therefore, the heating infrastructure no longer serves merely to generate and supply heat, but can also help ensure the stability of the entire energy system.

Biomass boiler and pipework at Teplárny Brno
The new biomass boiler at Teplárny Brno. Photo: Teplárny Brno.

How will this affect Brno’s future energy mix?

At present, natural gas still dominates the mix. In 2026, we will generate approximately 60 per cent of our heat from natural gas, with 25 per cent coming from waste-to-energy and 15 per cent from biomass. After 2032, the ratio should change significantly: we aim to obtain roughly half of our heat from Dukovany, 30 per cent from waste-to-energy, and 15 per cent from biomass. The share of natural gas should fall to approximately five per cent.

By sourcing 50 per cent of its heat from Dukovany, is the city not just swapping one form of dependence for another?

We do not want to replace our dependence on gas with another form of dependence. The aim is to create a more resilient system in which individual sources complement one another, and we can adapt their use to current needs. Today, we are the largest single consumer of natural gas in the Czech Republic, and the hot water pipeline alone can reduce our consumption by up to 77.7 million cubic metres a year. Brno is situated close to one of the country’s most significant and stable energy sources. Therefore, it makes sense to find a way to use the energy generated at Dukovany as efficiently as possible. Moreover, using heat from nuclear power stations to supply towns and cities is neither new nor untested. A hot-water pipeline from Temelín to České Budějovice has operated in the Czech Republic since 2023, and there is also experience of this abroad. For example, the Swiss REFUNA network has been utilising heat from the Beznau nuclear power station since the 1980s. The principle is, therefore, tried and tested, and we have a solid foundation on which to build. Our task is to utilise it in a way that best suits the conditions in Brno and its district heating system. In our case, the hot water pipeline is to have a capacity of 200 MW and the potential to supply Brno with up to two million gigajoules of heat per year. It can thus cover about half of Brno’s district heating needs while potentially reducing emissions by up to 135,000 tonnes of CO₂ per year.

The energy crisis has shown how important price is, alongside availability. What will the new mix bring in this regard?

Above all, greater predictability, as we are building a much more stable foundation for the long-term price of heat. Recent years have very clearly demonstrated how sensitive the price of natural gas can be to geopolitics, international markets or disruptions to supply chains. Furthermore, with fossil fuels, the costs associated with emissions allowances are passed on to the economy. The district heating network is designed as a strategic infrastructure with a lifespan of more than 60 years. When planning a system for such a long period, the stability of energy sources and the ability to spread risks matter as much as their current price.

What does such a large-scale project mean for financing and Teplárny Brno’s operations?

For the hot water pipeline, Teplárny Brno’s investment costs are set at CZK 17.8 billion. At the same time, ČEZ is investing in heat extraction technology at Dukovany. The financial model is based on grants from the Modernisation Fund that can reach up to CZK 10.6 billion. We will cover the remaining amount through loans and our own resources. The project also involves an organisational change. The founding of Teplárny Brno Distribuce is part of Teplárny Brno’s long-term plan to become a modern energy company; by separating the production, distribution, and sale of heat we are making each of these activities more transparent and thus laying the groundwork for further growth of the district heating system. The new company will be in charge of the main distribution network and will carry out the Dukovany–Brno hot water pipeline project. Meanwhile, the separation of the distribution business is a necessary condition for obtaining subsidy funding.

You are preparing the project jointly with ČEZ. How are your roles divided, and how far along are the preparations?

Our roles are divided quite naturally. ČEZ is responsible for supplying heat from the Dukovany Nuclear Power Station and for the associated modifications at the power station. We are preparing to transmit heat to Brno and integrate it into the city’s heating network. The main feeder to Bosonohy will be approximately 42 kilometres long. It will connect to roughly 53 kilometres of pipelines within the Brno area. AFRY CZ designed the main feeder. Design, planning permission, and land acquisition preparations are ongoing, and the current schedule anticipates completion of construction and the start of trial operations in 2032.

Why should the project also be of interest to companies and visitors to the International Industrial Fair?

Energy is a basic requirement for industrial competitiveness. It is necessary for companies to know where their energy will be obtained from, what its carbon footprint will be, whether the supplies will be stable, and whether the prices will be predictable in the long term.

The Dukovany–Brno hot water pipeline is one of the biggest energy projects at the present time being prepared in the Czech Republic, and its importance goes well beyond the heating industry alone. Yet it is also a major engineering project which will need the involvement of designers, power engineers, manufacturers of technology, construction companies, and providers of automation and control systems.

It is exactly projects of this kind that show that the energy transition is not only a necessity but also an opportunity for the Czech industry and its technical know-how.

Thank you for the interview.